Progress: Anuva Bento Integration
Product change
| Item | State | Evidence |
|---|---|---|
| Linear parent ANU-8 | In Progress | Linear issue |
| Product planning branch | Merged | Product Main PR #12, merged 2026-07-24 |
| Product plan preview | Approved | Change overview |
| Plan approval | Approved | Girish approved the plan as written on 2026-07-24 at 06:06 UTC |
| Planning PR | Merged | #12, merged at 2026-07-24 06:11 UTC |
| Bootstrap child | Done | ANU-9; Bento PR #1; Product Main PR #13; completion report |
| Feasibility spike | Done | ANU-10; Bento PR #2; completion evidence |
| Product go/no-go | Proceed | Decision, recorded 2026-07-25; Unity/Vuplex and performance testing deferred to ANU-15 |
| Production children | Ready | ANU-11 through ANU-16 are created and governed by their dependency graph |
| Product completion review | Not started | Gated on terminal required children |
Current decisions
- Approved: adopt an independent private
anuva-bentodownstream with preserved upstream ancestry. - Approved: treat Product Main invariants as normative while the downstream owns executable schemas, player/editor builds, templates, and artifacts.
- Approved: require one three-surface aggregate and one authoritative timeline.
- Approved: require Web/Unity exact-runtime parity, offline deterministic playback, and a clean development-phase Reveal cutover.
- Approved: bootstrap the new repository/harness before creating Bento-owned Linear issues.
- Approved: require a completed feasibility spike and a separate explicit Product Main go/no-go decision before production implementation starts.
- Approved on 2026-07-25: proceed from ANU-10 into production implementation based on the revised Web-feasibility evidence.
- Deferred from ANU-10: Unity/Vuplex verification and performance profiling. Both remain mandatory in ANU-15 and final ANU-8 acceptance.
Current gate
ANU-11 is the next unblocked implementation child. Starting it still requires the normal issue-start mutation and separate approval of its generated Implementation Plan. This proceed decision does not start any child automatically.
Next proposed sequence
- Start and deliver ANU-11 through its implementation-plan approval boundary.
- Deliver ANU-12 and ANU-13 after ANU-11.
- Deliver ANU-14 after ANU-12 and ANU-13.
- Deliver ANU-15 after ANU-11 and ANU-13, including the deferred Unity/Vuplex verification and three-WebView performance evidence.
- Deliver ANU-16 after ANU-13 and ANU-15.
- Perform the Product Main completion review only after every required child is terminal, then use the guarded ANU-8 Done transition.